Can additional current transformers (CT) be added to an Energy Meter that was purchased as a single phase, 1 CT meter?

Issue
User needs to add another CT to an Energy Meter.

Product Line
Energy Meter

Environment
Sub-metering

Cause
User may have ordered the wrong version of the Energy Meter for the system they are trying to monitor. Such as ordering a 2 CT version when a 3 CT version is needed.

Resolution
Energy Meters must be ordered based on the number of CTs and voltage connections required to monitor the electrical circuit. The Energy Meter can be ordered with 1, 2, or 3 CTs (Phase A, B, and C). All Energy Meters will have 3 voltage and current terminals no matter what model. Additional CTs cannot be added to the open CT connections. Each meter is calibrated and configured to monitor the specific system that it was designed for.

슈나이더 일렉트릭 Korea

자세히 알아보기
제품군
자세히 알아보기
제품군

도움이 필요하신가요?

  • 제품 선택기

    애플리케이션에 적합한 제품과 액세서리를 빠르고 쉽게 찾을 수 있습니다.

  • 견적 받기

    영업 관련하여 온라인으로 문의하시면 전문가가 연락드립니다.

  • 구매처

    해당 지역의 가장 가까운 슈나이더 일렉트릭 대리점을 쉽게 찾을 수 있습니다.

  • 지원 센터

    한 곳에서 모든 요구 사항에 대한 지원 리소스를 찾아보십시오.

  • 제품 문서
  • 소프트웨어 다운로드
  • 제품 선택기
  • 제품 대체 및 교체
  • 지원 및 연락처 센터
  • 영업소 검색
  • 견적 받기
  • 채용
  • 회사 소개
  • 부정 행위 보고
  • 접근성
  • 뉴스룸
  • 투자자
  • Ecostruxure
  • 작업 검색
  • 블로그
  • 개인정보 취급방침
  • 쿠키 공지
  • 사용 약관
  • Change your cookie settings