How to replace a serial meter with an Ethernet meter in Power SCADA Operation (PSO) 9.0.

Issue

A serial meter on an daisy chain was replaced with a new Ethernet meter. The Power SCADA Operation project must be updated so the new device communicates.

Product Line

Power SCADA Operations 8.2

Power Operation 2020 and 9.0

Power Operation 2021

Power Operation 2022

Power Operation 2023

Power Operation 2024

Environment

Device Manager

Device replacement

Resolution

  1. Open Power SCADA Studio.
  2. Go to Topology → I/O Devices and locate the row for the replaced device. Capture its parameters (I/O Server, Name, Protocol/Driver, etc.).
  3. Open I/O Device Manager (right‑side panel).
  4. In I/O Device Manager, select the active project → Manage a Single Device… → Remove one I/O device.
    • Complete the removal wizard and, when prompted, select Add / remove / update more equipment to continue.
  5. Choose Create one I/O device and select the correct device profile for the new Ethernet meter.
    • If the profile isn’t available, add it via Device Profile Editor, then export it to the project and return to I/O Device Manager. See FA404306 for instructions on how to add a device profile to a project.
    Reuse the exact same Equipment Name and I/O Device Name as the removed device to preserve existing tag/graphics bindings.
    • If the name differs (even syntax), a new tag set will be created and any graphics referencing the old tags would have to be edited.
  6. Select the same Primary Server (and Standby Server, if applicable) as the old device.
  7. Configure Modbus TCP communications (using the project’s Modbus driver—commonly PwrModbus when added via I/O Device Manager).
    • Enter the IP address of the meter and the Unit ID / Device Address required by the device:
      • Many TCP devices ignore Unit ID or expect 1.
      255 appears in some guides but is not universal.
      • For TCP→serial gateways, set the serial slave ID behind the gateway. Always follow the meter/gateway manual.
  8. Confirm the wizard’s Port Name; keep the new, unique name—do not reuse the old port name.
  9. Finish the I/O Device Manager workflow. Compile the project and restart the applicable I/O Server in Runtime so the device begins communicating.

Note: If the selected device profile adds driver parameters (timeouts, word‑order, etc.), review any driver/INI parameters in Setup Editor / citect.ini per the driver’s reference.

Recommendation:

If you are using an older version of

Power Operation, consider upgrading to the latest version for improved protocol support and security. For assistance with integration or upgrades, contact Schneider Electric Technical Support at: pmo-psup@se.com

Support details

슈나이더 일렉트릭 Korea

자세히 알아보기
제품군
자세히 알아보기
제품군

도움이 필요하신가요?

도움이 필요하신가요?

제품 선택기

제품 선택기

애플리케이션에 적합한 제품과 액세서리를 빠르고 쉽게 찾을 수 있습니다.

견적 받기

견적 받기

영업 관련하여 온라인으로 문의하시면 전문가가 연락드립니다.

구매처

구매처

해당 지역의 가장 가까운 슈나이더 일렉트릭 대리점을 쉽게 찾을 수 있습니다.

지원 센터

지원 센터

한 곳에서 모든 요구 사항에 대한 지원 리소스를 찾아보십시오.

  • 제품 문서
  • 소프트웨어 다운로드
  • 제품 선택기
  • 제품 대체 및 교체
  • 지원 및 연락처 센터
  • 영업소 검색
  • 견적 받기
  • 슈나이더 일렉트릭 커뮤니티
  • 채용
  • 회사 소개
  • 부정 행위 보고
  • 접근성
  • 뉴스룸
  • 투자자
  • Ecostruxure
  • 작업 검색
  • 블로그
  • 개인정보 취급방침
  • 쿠키 공지
  • 사용 약관
  • Change your cookie settings