I do not see any status after exporting my switchboard to Facility Expert
EcoStruxure Power Commissioning tool sometimes does not show any status after exporting the project to Facility Expert. Status here is the Orange when export is "In progress" and Green when it is "Success" (highlighted in below screen shots). But after exporting you will see all the switchboards and its assets in Facility Expert account.
In-Progress status :

Success status:

Why this issue?:
When you cannot see any status (which are given in above screen shots) after you export your project from EPC to Facility Expert, the reason is due to the number of characters you have given(alpha numeric) in your project details sections. If there are mote than 4000 characters (taking into account all text fields you have typed), you will see this kind of issue.
How to troubleshoot? :
When you encounter such issue, you can check the EcoStruxure Power Commission logs for the below error message: "The field Description must be a string or array type with a maximum length of '4000'."
With this error in the logs, you should be able to understand that you have exceeded the 4000 characters in the project details and End user site information details.
How to recover or prevent such issues:
To prevent this issue, you need to ensure that while typing the data in the text fields of the Project details and End user Site details , together should not exceed more than 4000 characters (Text fields are shared in below screen shot):
Project information :

End user Site details:

Also as a pre-requisite, you need to check the number of devices you have added in your project.
The recommended maximum number of devices you can add in your project can be seen in the help section of the EPC application or as shown in below screen shot:

In-Progress status :
Success status:
Why this issue?:
When you cannot see any status (which are given in above screen shots) after you export your project from EPC to Facility Expert, the reason is due to the number of characters you have given(alpha numeric) in your project details sections. If there are mote than 4000 characters (taking into account all text fields you have typed), you will see this kind of issue.
How to troubleshoot? :
When you encounter such issue, you can check the EcoStruxure Power Commission logs for the below error message: "The field Description must be a string or array type with a maximum length of '4000'."
With this error in the logs, you should be able to understand that you have exceeded the 4000 characters in the project details and End user site information details.
How to recover or prevent such issues:
To prevent this issue, you need to ensure that while typing the data in the text fields of the Project details and End user Site details , together should not exceed more than 4000 characters (Text fields are shared in below screen shot):
Project information :
End user Site details:
Also as a pre-requisite, you need to check the number of devices you have added in your project.
The recommended maximum number of devices you can add in your project can be seen in the help section of the EPC application or as shown in below screen shot:
게시 대상: 슈나이더 일렉트릭 Korea




도움이 필요하신가요?
제품 선택기
애플리케이션에 적합한 제품과 액세서리를 빠르고 쉽게 찾을 수 있습니다.
견적 받기
영업 관련하여 온라인으로 문의하시면 전문가가 연락드립니다.
구매처
해당 지역의 가장 가까운 슈나이더 일렉트릭 대리점을 쉽게 찾을 수 있습니다.
지원 센터
한 곳에서 모든 요구 사항에 대한 지원 리소스를 찾아보십시오.