How we can see CT Connection Reversal with EM1000 or EM1200 or EM1220 display ?

CT Connection Reversal
To check the polarity of the CT after the meter has been installed, go to the DIAG (diagnostic) pages and check the CT REV display page. Refer to “EM1000/EM1200/EM1220 Power and Energy Meters Menu Hierarchy” on  for more information.
Assuming that you are consuming power (import), check for one of the following conditions in the meter:
1. If the display shows L 1 or L 2 or L 3, then CT phase 1 or CT phase 2 or CT phase 3 is reversed and the corresponding CT phase must be corrected.
2. If the display shows L 12 or L 23 or L 32, then CT phases (1 and 2) or CT phases (2 and 3) or CT phases (3 and 1) are reversed and the corresponding CT phases must be corrected.
3. If the display shows L 123, then all the phases are reversed and must be corrected.
4. If the display shows L-, then no CTs are reversed.

Schneider Electric Belgium

En savoir plus

En savoir plus

Besoin d'aide ?

Sélectionnez le bon produit

Trouvez rapidement et facilement les produits et accessoires adaptés à vos applications.

Obtenir un devis

Effectuez une demande de renseignements en ligne et un expert vous contactera.

Où acheter ?

Trouvez facilement le distributeur Schneider Electric local le plus proche.

Centre d'aide

Trouvez des ressources de support pour tous vos besoins, en un seul endroit.