How to start with a very first new Safety M580 CPU into a Safety configuration ?
1/ Set the date and time into the PLC , CPU out of the final destinated rack ,
2/ Set an NTP server into the configuration (either external server or CPU as NTP server),
3/ Place CPU into the rack to be used and start the configuration,
4/ Make sure all configured safety I/O modules are unlocked ( eventually, use the top blue button to unlock the locked module )
Reminder : it is required to set the date and time into the PLC in order to have a reliable safe communication between CPU and safety IOs module.
If the configuration with Safety I/Os have been started before the configuration of the time into the CPU, a synchronization of the time between IOs and CPU is necessary either by :
- 1: forcing the time using %SW128 see the FA333333 how to proceed
- 2: downloading again the application into the PLC
- 3 : doing a power cycle of the entire configuration (CPU AND IOs safety modules)
Publié pour: Schneider Electric Belgium


Besoin d'aide ?
Sélectionnez le bon produit
Trouvez rapidement et facilement les produits et accessoires adaptés à vos applications.
Obtenir un devis
Effectuez une demande de renseignements en ligne et un expert vous contactera.
Où acheter ?
Trouvez facilement le distributeur Schneider Electric local le plus proche.
Centre d'aide
Trouvez des ressources de support pour tous vos besoins, en un seul endroit.