How to start with a very first new Safety M580 CPU into a Safety configuration ?
1/ Set the date and time into the PLC , CPU out of the final destinated rack ,
2/ Set an NTP server into the configuration (either external server or CPU as NTP server),
3/ Place CPU into the rack to be used and start the configuration,
4/ Make sure all configured safety I/O modules are unlocked ( eventually, use the top blue button to unlock the locked module )
Reminder : it is required to set the date and time into the PLC in order to have a reliable safe communication between CPU and safety IOs module.
If the configuration with Safety I/Os have been started before the configuration of the time into the CPU, a synchronization of the time between IOs and CPU is necessary either by :
- 1: forcing the time using %SW128 see the FA333333 how to proceed
- 2: downloading again the application into the PLC
- 3 : doing a power cycle of the entire configuration (CPU AND IOs safety modules)
Gepubliceerd voor: Schneider Electric Belgium


Hulp nodig?
Selecteer zelf het juiste product
Vind snel en eenvoudig de juiste producten en toebehoren voor uw toepassingen.
Offerte aanvragen
Dien uw aanvraag online in en een expert zal contact met u opnemen.
Verkooppunten
Vind eenvoudig de dichtstbijzijnde distributeur van Schneider Electric op uw locatie.
Help Center
Vind de antwoorden die u nodig heeft via bladeren door veelgestelde vragen over onderwerpen.