Can you share existing metering CT's with an AccuSine PCS+?
Issue
There may not be room in the switchgear for another set of CT's so it is possible to use an existing set CT's. An example would be if there is a set of CT's for a power meter already installed in the gear.
Product Line
AccuSine PCS+
Resolution
Attached is an example wiring diagram showing how the existing metering CT's can be wired to the AccuSine from the power meter. These CT's need to be wired in series to the AccuSine from the power meter. It will not work correctly if wired in parallel.
There may not be room in the switchgear for another set of CT's so it is possible to use an existing set CT's. An example would be if there is a set of CT's for a power meter already installed in the gear.
Product Line
AccuSine PCS+
Resolution
Attached is an example wiring diagram showing how the existing metering CT's can be wired to the AccuSine from the power meter. These CT's need to be wired in series to the AccuSine from the power meter. It will not work correctly if wired in parallel.
Udgivet til: Schneider Electric Danmark
Brug for hjælp?
Produktvælger
Find hurtigt og nemt de rette produkter og det rette tilbehør til dine anvendelser.
Få et tilbud
Start din salgsforespørgsel online, så vil du blive kontaktet af en ekspert.
Find forhandler
Find den nærmeste Schneider Electric-distributør.
Hjælpecenter
Find supportressourcer til alle dine behov på ét sted.