PC/104 Card Stacking for SAGE RTU CPU Upgrades
Issue
Users need guidance on the correct stacking order of PC/104 cards when installing or upgrading the CPU in SAGE RTU units.
Product
SAGE RTU Product Line (models using PC/104 architecture, including C3414 CPU upgrades)
Environment
Utility substations or industrial automation systems where SAGE RTUs require CPU upgrades or additional PC/104 expansion modules.
Cause
Incorrect stacking of PC/104 cards can lead to clearance issues, improper connections, or malfunction of optional modules such as Ethernet or GPS.
Resolution
When stacking PC/104 cards:
- Place the CPU card on top of the stack for standard installations.
- If installing the C3463 Ethernet 5-Port Switching Hub, it must be placed on top of the CPU card due to clearance restrictions.
- Other optional cards (e.g., C3461 GPS, C3830 Analog Input, C3831 IRIG-B, C3437 Communication Expansion) should be stacked below the CPU card in any order, except where noted.
- Ensure all connectors are properly aligned and secured using the provided mounting hardware.
Refer to next Figure for the recommended stacking layout:
Yayımlanma amacı: Schneider Electric Turkey
Yardıma mı ihtiyacınız var?
Ürün seçici
Uygulamalarınız için doğru ürünleri ve aksesuarları hızlı ve kolay bir şekilde bulun.
Teklif Alın
Satışla ilgili sorularınızı çevrimiçi olarak başlatın, bir uzman sizinle bağlantı kuracaktır.
Satış noktaları
Konumunuza en yakın Schneider Electric distribütörünü kolayca bulun.
Yardım Merkezi
Tüm ihtiyaçlarınız için destek kaynaklarını tek bir yerde bulun.