On a M580 Hotstandby system, why the application cannot be transferred from Primary to Standby?
The M580 redundant system is made in a way that data related to tasks are exchanged between the Primary controller to the Standby at every cycle.

Synchronized situation :
At each cycle:
-          The Primary CPU “packs” the data in preparation to the transfer
-          The Primary CPU then starts to execute the application code of the task, and in parallel the data is being transferred to the Standby
-          Once the data are received, the Standby unpacks the data, and start executing its local code (depending on the configuration)
All of this should happen within the configured task (Mast of Fast) period in Unity Pro.

In this situation, simultaneous spare time exist in both CPUs at the end of the cycle, and an application transfer (low priority) can be managed by the system.

Not synchronized situation :
Depending on the tasks (mast of fast) execution duration, on the data transfer duration, and on the associated chosen periods, it is possible that the duration of the data transfer exceeds the task period, even if the primary tasks durations are lower than the period settings.
in this case, the primary CPU will not receive the data transfer acknowledge from the standby CPU, => the status of the standby task will be “not synchronized”.

In this situation, no simultaneous spare time exist in both CPU at the end of the tasks, and no application transfer can be managed by the system.

In order not to jeopardize the system, the Standby CPU will remain Standby, however, the indication that the data was not fully received during this cycle will be available in the system bit: ECPU_HSBY_1.MAST_SYNCHRONIZED (or ECPU_HSBY_1.FAST_SYNCHRONIZED)

According to your process, having the data not synchronized between Primary and Standby for several cycles might have an impact on your application. For instance, the system might not have enough time to transfer the application from Primary to Standby.

in order to analyze if there could be an impact, do the following:
-          Get the system in a stable state (Run Primary and Run Standby)
-          Connect to the Primary CPU with Unity Pro
-          Observe the Device DDT bit: MAST_SYNCHRONIZED and / or FAST_SYNCHRONIZED (if FAST used)
-          If MAST_SYNCHRONIZED and / or FAST_SYNCHRONIZED do not always show value = 1, then adjust the configured period online until this cycle is stable and MAST/FAST_SYNCHRONIZED are set to 1

another advice is to use these system bits in the logic of the application or in the Scada in order to trigger warnings
Feel free to contact your local Schneider Electric representative for additional information.

施耐德電機Taiwan

探索更多
系列:
探索更多
系列:
  • 產品文檔
  • 軟體下載
  • 產品選型工具
  • 產品替代和替換
  • 幫助和聯絡中心
  • 尋找我們的辦公室
  • 取得報價
  • 施耐德電機社群
  • 人才招募
  • 公司簡介
  • 舉報不當行為
  • 無障礙
  • 新聞中心
  • 投資者
  • 專業洞察
  • 台灣施耐德電機學院
  • 綠色影響力落差調查
  • Schneider Go Green 2025
  • 隱私政策
  • Cookie通告
  • 使用條款
  • Change your cookie settings