Issue:
Ground fault testing of circuit breakers
Product Line:
Circuit Breakers
Resolution:
Schneider Electric recommends primary injection testing to comply with the requirements of NEC 230.95(C) for ground fault testing upon installation. Secondary injection testing may be done at the option of the customer for scheduled maintenance after the installation has been tested and commissioned.
For test procedures, please consult the Field Test and Maintenance Guide.
Ground fault testing of circuit breakers
Product Line:
Circuit Breakers
Resolution:
Schneider Electric recommends primary injection testing to comply with the requirements of NEC 230.95(C) for ground fault testing upon installation. Secondary injection testing may be done at the option of the customer for scheduled maintenance after the installation has been tested and commissioned.