How to install Accusine PCS+ CT's for a Main-Tie-Main Installation

Issue
Example drawings for how to connect CT's for a Main-Tie-Main AccuSine PCS+ installation are not shown in the wiring diagrams in the installation guide.

Product Line
AccuSine PCS+

Resolution
Attached is an example wiring diagram showing the placement and polarity of the CT's for a Main-Tie-Main installation.  The polarity of the CT's on either side of the tie-breaker must be opposite the polarity of the CT's after the main breaker on each side.  This will allow each AccuSine to correct only the side it is installed on.