Smart UPS Modular Ultra display remains blank

Issue:

The UPS display is blank and will not respond


Product Line:

Smart UPS Modular Ultra


Environment:

All models, all serial numbers


Resolution:

If the display is blank on startup or after a display/NMC reboot and the NMC status LED (behind the door to the right of the display) is:

  1. solid orange, this usually indicates the display firmware is stuck in the boot loader. Press and hold the Reset button (located in the pinhole) until the LED changes from solid orange and begins progressing through other LED states. During the recovery process, the LED may:
    1. Change from solid orange to flashing green.
    2. After approximately 20 seconds, change to flashing orange.
    3. Turn off completely after the Reset button is released.
    4. Remain off for several minutes before resuming normal startup activity.
    5. Progress through additional orange and green LED indications before the display powers on.
    6. Important: Do not assume the recovery procedure has failed if the LED turns off after releasing the Reset button. Allow several minutes for the display to complete its recovery and boot sequence. The display may not become active immediately.
  2. on and doing something other than indicating solid orange, the wrong firmware is most likely installed on the display.  Check the currently installed NMC/Display firmware on the UPS via the console port to the right of the display.  After, please install the correct NMC/Display firmware
  3. completely off, check the connections to the back of the display.  The mini HDMI cable might be disconnected.  You may also look for any damage to the cables/connections.

If none of these address the blank screen, please contact the Customer Care Center to get the display replaced.

施耐德電機Taiwan

探索更多
系列:
探索更多
系列:
  • 產品文檔
  • 軟體下載
  • 產品選型工具
  • 產品替代和替換
  • 幫助和聯絡中心
  • 尋找我們的辦公室
  • 取得報價
  • 施耐德電機社群
  • 人才招募
  • 公司簡介
  • 舉報不當行為
  • 無障礙
  • 新聞中心
  • 投資者
  • 專業洞察
  • 台灣施耐德電機學院
  • 綠色影響力落差調查
  • Schneider Go Green 2025
  • 隱私政策
  • Cookie通告
  • 使用條款
  • Change your cookie settings