Issue:
Need to confirm proper installation per OSHPD and IBC High Seismic Area.
Product Line:
NetShelter SX
Environment:
All versions and serial ranges.
Cause:
The NetShelter SX OSHPD and IBC Structural Calculations documents do not mention if the leveling feet must be down.
Resolution:
The calculations are all based on the anchorage points in the floor and the cabinet, but as in any installation it's always the best practice (recommended) to have the leveling feet down.
Please see the attachment for a good graphic representation of this question.
Need to confirm proper installation per OSHPD and IBC High Seismic Area.
Product Line:
NetShelter SX
Environment:
All versions and serial ranges.
Cause:
The NetShelter SX OSHPD and IBC Structural Calculations documents do not mention if the leveling feet must be down.
Resolution:
The calculations are all based on the anchorage points in the floor and the cabinet, but as in any installation it's always the best practice (recommended) to have the leveling feet down.
Please see the attachment for a good graphic representation of this question.
Publikováno pro: Schneider Electric Česká republika


Potřebujete pomoc?
Nástroj pro výběr produktů
Rychle a snadno vyhledávejte správné produkty a příslušenství pro vaše aplikace.
Získejte nabídku
Poptejte nás online a náš lokální specialista se s vámi spojí!
Kde nakoupit?
Jednoduše najděte nejbližšího distributora výrobků Schneider Electric ve vašem okolí.
Centrum nápovědy
Zdroje podpory pro všechny své potřeby najdete na jednom místě.