How to interpret the information of the diagnosis indication ? Does it give the pole condition for all 3 poles ? What if the TeSys Giga contactor is only use 2 poles in the given application ? (Like to control single phase load/DC application).

Article available in these languages: Nizozemština

The indication is calculated globally, for all the 3 poles. If the application uses only 2 poles, we recommend removing the non-used pole (central one). Otherwise the wear diagnosis indication will not work.

Schneider Electric Česká republika

How to interpret the information of the diagnosis indication ? Does it give the pole condition for all 3 poles ? What if the TeSys Giga contactor is only use 2 poles in the given application ? (Like to control single phase load/DC application).

Article available in these languages: Nizozemština

The indication is calculated globally, for all the 3 poles. If the application uses only 2 poles, we recommend removing the non-used pole (central one). Otherwise the wear diagnosis indication will not work.
 

Schneider Electric Česká republika

Zjistěte více
Řada:
Zjistěte více
Řada:
Zjistěte více
Řada:
Zjistěte více
Řada:
move-arrow-top
Your browser is out of date and has known security issues.

It also may not display all features of this website or other websites.

Please upgrade your browser to access all of the features of this website.

Latest version for Google Chrome, Mozilla Firefox or Microsoft Edgeis recommended for optimal functionality.
Your browser is out of date and has known security issues.

It also may not display all features of this website or other websites.

Please upgrade your browser to access all of the features of this website.

Latest version for Google Chrome, Mozilla Firefox or Microsoft Edgeis recommended for optimal functionality.