Unique ID Expected. Please Run Migration Tool (W1050)
Issue
After upgrading a project, I receive the error Unique ID Expected. Please Run Migration Tool (W1050).
Product Line
Power Scada Operation 2020
Power Scada Operation 2020 R2
Power Scada Operation 2021
Ecostruxure Power Operation 2022
Ecostruxure Power Operation 2024
Environment
Power Operation Studio Compiler
Cause
When upgrading a project to the current Power Operation version, the project must be properly migrated. The custom included projects must also be run through the Power Operation Migration Tool. Please reference the Upgrade process for Power Operation for more information.
Unique ID's are distinct identifiers linked to equipment and variables. Unique identifiers allow for more seamless integration for future versions. Unique IDs also hold information relating to how the object should be formatted. When a Unique ID has been improperly migrated this error will be thrown.
Resolution
Confirm the project has been properly migrated as laid out in the Upgrade process.
If the problem persists or the offending object is in a project that is not a selectable project, running Repair Unique ID should fix the problem.
Publikováno pro: Schneider Electric Česká republika
Potřebujete pomoc?
Nástroj pro výběr produktů
Rychle a snadno vyhledávejte správné produkty a příslušenství pro vaše aplikace.
Získejte nabídku
Poptejte se nás online a náš lokální specialista se s vámi spojí!
Kde nakoupit?
Jednoduše najděte nejbližšího distributora výrobků Schneider Electric ve vašem okolí.
Centrum nápovědy
Zdroje podpory pro všechny své potřeby najdete na jednom místě.