How to execute the GET_TS_EVT_M on a M580 redoundant PLC ?
GET_TS_EVT_M function block be executed in a Modicon M580 Redundant system to retrieve timestamped events ?In an M580 Redundant system, the GET_TS_EVT_M function block must be executed only by the Primary CPU, as recommended on page 214 of the EcoStruxure Control Expert System Bloc Library attached:
The application should check the Redundant operating state before executing the function block. The call to GET_TS_EVT_M must be enabled when the local CPU is operating as the Primary CPU and disabled when the local CPU is operating as the Standby CPU.
This prevents both CPUs from executing the timestamped-event retrieval operation at the same time and avoids duplicate or inconsistent event processing.
If a switchover occurs, the former Standby CPU becomes the new Primary CPU. Once the new CPU reaches the Primary operating state, the application can resume execution of the GET_TS_EVT_M function block.
The following implementation principles should therefore be applied:
- Determine whether the local M580 CPU is currently the Primary CPU.
- Execute
GET_TS_EVT_Monly when the Primary status is active. - Do not execute the function block on the Standby CPU.
- After a Redundant switchover, allow the new Primary CPU to resume the function block execution.
- Ensure that the function block input and output variables are managed consistently during the switchover.
Publikováno pro: Schneider Electric Česká republika
Zjistěte více
Řada:
Zjistěte více
Řada:
Potřebujete pomoc?
Nástroj pro výběr produktů
Rychle a snadno vyhledávejte správné produkty a příslušenství pro vaše aplikace.
Získejte nabídku
Poptejte se nás online a náš lokální specialista se s vámi spojí!
Kde nakoupit?
Jednoduše najděte nejbližšího distributora výrobků Schneider Electric ve vašem okolí.
Centrum nápovědy
Zdroje podpory pro všechny své potřeby najdete na jednom místě.