How can the Advantys STBNIC2212 V3 be replaced with a V4 module in a CE application?
- Open the DTM in the CE application.
- Click on Start Advantys to start tthe Advantys Configuration software and link it with the DTM..
- Right click on the STBNIC2212.
- Select 'Replace NIM'.
- Replace the STBNIC2212 V3 with the V4 module.
- Save the changes.
- Build the Advantys application.
- Save the changes.
- Set the rotary switches on the V4 module to the same position that was on the V3 module.
- Power cycle theSTBNIC2212.
- If the rotary switch is set to the 'Stored' position: (See below)
- Open the web page for the STBNIC2212.
- Assign the same IP address and
- Leave the Device name blank in the web pages for the to the new STBNIC2212 .
- Power Cycle the STBNICC2212.
- Ensure that the Advantys island is in a ready state..
- Go back to CE.
- Apply the changes to the DTM.
- Rebuild.
- Save the changes.
- Connect to the M580 PLC.
- Transfer the CE application to the PLC.
- Connect to the STBNIC2212.
Publicerad för: Schneider Electric Sverige


Behöver du hjälp?
Produktväljare
Hitta snabbt och enkelt rätt produkter och tillbehör för dina ändamål.
Begär en offert
Ställ din fråga online så kontaktar vi dig.
Här köper du
Hitta enkelt närmaste Schneider Electric-distributör på din ort.
Hjälpcenter
Hitta alla supportresurser som du behöver på ett ställe.