What could cause a M580 safety PLC safe task to come up in STOP mode after a power cycle?

Issue:

possible cause of M580 safety PLC safe task to come up in STOP mode after a power cycle


Product Line:

M580 Safety PLC, Ecostruxure Control Expert


Resolution:

One possible cause of the safety Task to come up in STOP mode is if the  "support quantum remote drops" option in the processor configuration is selected and there is no Quantum drop configured in the projectimage1

Uncheck the "Support Quantum Remote drops" option in the processor configuration. This is would be an offline change and thus require a project download to the PLC.

image2

Schneider Electric Sverige

Utforska mer
Produkt:
Utforska mer
Produkt:
  • Produktdokumentation
  • Ladda ner programvara
  • Produktväljare
  • Byt ut eller ersätt produkt
  • Hjälp- och kontaktcenter
  • Här köper du
  • Begär en offert
  • Hitta våra kontor
  • Shop.se.com/se/sv nedstängning
  • Schneider Electrics community
  • Karriär
  • Företagsprofil
  • Rapportera ett tjänstefel
  • Tillgänglighet
  • Pressrum
  • Investerare
  • EcoStruxure
  • Sök jobb
  • Blogg
  • Sekretesspolicy
  • Cookie-information
  • Användarvillkor
  • Change your cookie settings