Why does Control Expert display a CPU load 90% when the PLC is configured in Cyclic mode?
Issue:
Starting with Control Expert V16.4, a CPU load indicator is displayed in the status bar when connected to a PLC. When the MAST task is configured in Cyclic mode, the CPU load indicator is displayed in orange at 90%, even for a simple or empty application. This behavior may be interpreted as a controller overload, although it is expected.
Environnement:
- Control Expert V16.4 and later
- PLC configured with a Cyclic MAST task
Resolution:
This behavior is expected and does not indicate a controller overload.
The CPU load indicator displayed in the Control Expert status bar reflects the value of%SW116 (Total System CPU Load). When the MAST task is configured in Cyclic mode, the controller continuously executes the application without any idle time between scans. Consequently,%SW116 reports a CPU load of approximately 90%, even for simple or empty applications.
In Periodic mode, the CPU load is generally more representative of the actual processing margin because task execution is based on a configured period.
Publicerad för: Schneider Electric Sverige
Utforska mer
Produktfamilj
Utforska mer
Produktfamilj
Behöver du hjälp?
Produktväljare
Hitta snabbt och enkelt rätt produkter och tillbehör för dina ändamål.
Begär en offert
Ställ din fråga online så kontaktar vi dig.
Här köper du
Hitta enkelt närmaste Schneider Electric-distributör på din ort.
Hjälpcenter
Hitta alla supportresurser som du behöver på ett ställe.