The Fast Trans range of transformers which are liquid filled free breathing distribution transformers covers following kVA ratings and the number of Low Voltage cables that can be connected within the LV cable box varies for each rating as detailed below :-
315kVA One single core cable per phase and one on the neutral ( 4 single core cables total)
500kVA One single core cable per phase and one on the neutral ( 4 single core cables total)
800kVA Two single core cables per phase and one on the neutral ( 7 single core cables total)
1000kVA Two single core cables per phase and one on the neutral ( 7 single core cables total)
1250kVA Two single core cables per phase and one on the neutral ( 7 single core cables total)
1500kVA Three single core cables per phase and two on the neutral ( 11 single core cables total)
1600kVA Three single core cables per phase and two on the neutral ( 11 single core cables total)
2000kVA Four single core cables per phase and two on the neutral ( 14 single core cables total)
The above number of LV cables are the standard arrangement. If alternative cable arrangements be required this should be discussed at the time of transformer tendering.
315kVA One single core cable per phase and one on the neutral ( 4 single core cables total)
500kVA One single core cable per phase and one on the neutral ( 4 single core cables total)
800kVA Two single core cables per phase and one on the neutral ( 7 single core cables total)
1000kVA Two single core cables per phase and one on the neutral ( 7 single core cables total)
1250kVA Two single core cables per phase and one on the neutral ( 7 single core cables total)
1500kVA Three single core cables per phase and two on the neutral ( 11 single core cables total)
1600kVA Three single core cables per phase and two on the neutral ( 11 single core cables total)
2000kVA Four single core cables per phase and two on the neutral ( 14 single core cables total)
The above number of LV cables are the standard arrangement. If alternative cable arrangements be required this should be discussed at the time of transformer tendering.