Ecostruxure Automation Expert [22.0]: How to set M580 controller to automatically Run after deployment
This document explains user on how to set M580 controller to automatically Run after deployment.
By default, the M580 Controller will be in STOP mode after successful project deployment and User needs to manually RUN the Controller by giving another Command.
However, User can set the Controller to automatically RUN after Deployment. This can be done by setting the below shown Device configuration settings in Logical devices tab.
By default, the M580 Controller will be in STOP mode after successful project deployment and User needs to manually RUN the Controller by giving another Command.
However, User can set the Controller to automatically RUN after Deployment. This can be done by setting the below shown Device configuration settings in Logical devices tab.
Publicerad för: Schneider Electric Sverige


Behöver du hjälp?
Produktväljare
Hitta snabbt och enkelt rätt produkter och tillbehör för dina ändamål.
Begär en offert
Ställ din fråga online så kontaktar vi dig.
Här köper du
Hitta enkelt närmaste Schneider Electric-distributör på din ort.
Hjälpcenter
Hitta alla supportresurser som du behöver på ett ställe.