    Queensland Rail: Customer Story Key Outcomes

    • Default Alternative Text Reduced delays on Queensland Rail's busy inner-city network
    • Default Alternative Text Increased network reliability for the 2018 Commonwealth Games and 1.5 million extra visitors
    • Default Alternative Text Smooth implementation of the solution, minimizing interruptions to commuters
    Default Alternative Text

    Upgrade your aging equipment

    Discover the benefits of modernizing your existing LV and MV switchgear to help cut costs and boost reliability. Download white paper
    • Keeping the trains on track

      EcoStruxure helped Queensland Rail improve the reliability of its services in time for the 2018 Commonwealth Games.

    Discover EcoStruxure

    Learn how your business can achieve success with EcoStruxure: Innovation at Every Level.
    Explore more

    The Challenge

    • Reduce the number of power incidents which caused delays on Queensland Rail’s busy inner-city network in Brisbane

    • Build a more reliable system to help cope with 1.5 million extra visitors to the 2018 Commonwealth Games

    • Install a new substation at Brisbane’s Fortitude Valley station, in a space allowing for just a 24-square foot (7.3 m2) container

    • Carry out the work with minimal disruption to passengers
    Default Alternative Text

    The Solution

    Reliability with EcoStruxure Power 

    Edge Control: Citect SCADA 
    Connected Products: GHA Rail, Gutor PXC, Compact NSX 

    • A new substation using a range of solutions based on EcoStruxure Power
    • These included the GHA Rail gas-insulated switchgear, MiCOM protection relays, a Gutor PXC industrial UPS system, Compact NSX circuit breakers, a compact LV Spacial SF enclosure, and Citect SCADA monitoring and control software
    Default Alternative Text

    The Results

    • Minimized on-site work during the upgrade, avoiding as many interruptions to commuters as possible

    • Reduction in the number of incidents which impact the entire inner-city network, resulting in fewer delays to commuter services

    • Overcame the challenge of ensuring power reliability for 1.5 million extra passengers during the Commonwealth Games
    Default Alternative Text
    Two people wearing hi vis clothing at facility

    “We have increased patronage on the trains and we need more trains and more power to cope with the demand.”

    Paul Rourke, Project Manager, Queensland Rail

    Discover our offer